Risk Mitigation when Microtunneling in Adverse Soil and Rock Conditions: A Case Study

机译:在不利土壤和岩石条件下微隧道危险的风险减缓:一个案例研究

获取原文

摘要

In 2010 Stantec was awarded the environmental assessment (EA), detailed design and contract administration for the City of Kawartha Lakes’ Northwest Trunk Sewer project, which included installation and replacement of 4.5 km of gravity sewer and 6 km of forcemain. The City of Kawartha Lakes relied on Federal Infrastructure stimulus funding for this project which was provided with strict project completion timelines. This led to an accelerated project schedule. To facilitate efficient construction schedules, the project was split into six (6) independent contracts, the most complex of which included a twin 500 mm diameter concrete pressure pipe (CPP) forcemain installation over a 220 m crossing of the Scugog River by microtunneling. Given the scale of the project, the presence of provincially significant wetlands in the region, and potentially contaminated sediments across the Scugog river crossing, it was imperative to minimize risks and project delays.
机译:2010年,Stantec被授予了科拉那湖城市西北地区下水道项目的环境评估(EA),详细的设计和合同管理,包括安装和更换4.5公里的重心下水道和6公里的灭鼠。 Kawartha市湖泊依靠该项目的联邦基础设施刺激资金,该项目提供了严格的项目完成时间表。这导致了加速的项目时间表。为了便于高效的施工时间表,该项目分为六(6)个独立合同,其中最复杂的是,其中包括双500毫米直径的混凝土压力管(CPP)通过Microtunneling在220米的巡回河交叉口上进行安装。鉴于该项目的规模,该地区普遍湿地存在普遍湿地,潜在污染的沉积物横跨普通河流,势在必使风险和项目延误最大限度地实现。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号