Cursed BassGas starts sales at last

机译:Cursed BassGas最后开始销售

获取原文
获取原文并翻译 | 示例
           

摘要

Its two years behind schedule and there has been a 300 million blow out in the budget,but the beleaguered BassGas project has finally started sales of gas and liquids and most of the facilities have been commissioned.Raw gas from the Yolla-A platform in Bass Strait was introduced to the onshore processing plant at Lang Lang in early May with the first gas sold into the Victorian grid several weeks later.
机译:它的进度落后了计划两年,预算中有3亿美元的损失,但饱受困扰的BassGas项目终于开始销售天然气和液体,大部分设施已经调试完毕.Bass的Yolla-A平台的原始天然气海峡于5月初被引入郎朗的陆上加工厂,几周后,第一批天然气被出售给维多利亚州电网。