Its two years behind schedule and there has been a 300 million blow out in the budget,but the beleaguered BassGas project has finally started sales of gas and liquids and most of the facilities have been commissioned.Raw gas from the Yolla-A platform in Bass Strait was introduced to the onshore processing plant at Lang Lang in early May with the first gas sold into the Victorian grid several weeks later.