Research On Duration Estimation Of Ling Shan Tunnel Engineering

机译:灵山隧道工程工期估算研究

获取原文

摘要

The South-to-North Water Diversion is a tough and groundbreaking project of a province.Ling Shan tunnel is a key engineering which has many uncertain factors and complex problems in construction.In order to implement the project smoothly,is worth to research how to establish a scientific and reasonable construction schedule.The paper is based on the data of five similar tunnel engineerings,applying information diffusion theory to the construction progress network diagram so as to estimate main work time and determine the key circuit.Therefore,the project managers can calculate the total duration of Ling Shan tunnel engineering more accurately and offer reliable evidence for the follow-up ' engineerings.
机译:南水北调是一个省的一项艰巨而开创性的工程。灵山隧道是一项关键工程,施工过程中存在诸多不确定因素和复杂问题。为使工程顺利实施,值得研究。本文基于五个相似隧道工程的数据,将信息扩散理论应用于施工进度网络图,以估算主要工作时间并确定关键电路。因此,项目经理可以更准确地计算灵山隧道工程的总工期,并为后续工程提供可靠的证据。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号