The Seli joint venture has completed tunnel excavation on the Passirio (Val Passiria) small hydro project in Italy with the breakthrough of the 3.7m diameter double shield universal (DSU) TBM for the headrace drive. Seli modified a Wirth double shield for the 5,885m long headrace tunnel excavation, which took 12 months to complete. Average advance during the bore was 500m per month, though inflows up to 400 l/s slowed progress at times.