A Proposal for the Improvement of Project's Cost Predictability Using Earned Value Management and Historical Data of Cost - An Empirical Study

机译:利用挣值管理和成本历史数据改善项目成本可预测性的建议-实证研究。

获取原文
获取原文并翻译 | 示例
           

摘要

Although the Earned Value Management (EVM) technique has been used by several companies in various industrial sectors (software development, construction, aerospace, aeronautics, among others) for over 35 years to predict time and cost outcomes, many studies have found vulnerabilities, including: (ⅰ) cost performance data do not always have normal distribution, which makes reliable projections difficu (ⅱ) instability of cost performance indexes during the execution of projects, (ⅲ) there is a worsening tendency in cost performance indexes when project approaches termination. This paper proposes an extension of the EVM technique through the integration of historical cost performance data of processes as a means to improve the project's cost predictability. The proposed technique was evaluated through an empirical study, which evaluated the implementation of the proposed technique in 22 software development projects. The proposed technique has been applied in real projects with the aim of evaluating the accuracy and variation compared to the traditional technique. Hypotheses tests with 95% significance level were performed, and the proposed technique was more accurate and more precise than the traditional technique for calculating the Cost Performance Index (CPI) and Estimates at Completion (EAC).
机译:尽管挣值管理(EVM)技术已在多个行业(软件开发,建筑,航空航天,航空等领域)的多家公司中使用,以预测时间和成本结果超过35年,但许多研究发现了漏洞,包括:(ⅰ)成本绩效数据并不总是呈正态分布,这使得可靠的预测变得困难; (ⅱ)项目执行期间成本绩效指标的不稳定性;(ⅲ)当项目接近终止时,成本绩效指标有恶化的趋势。本文提出了通过集成过程的历史成本绩效数据来扩展EVM技术的方法,以提高项目成本的可预测性。通过一项实证研究对提出的技术进行了评估,该研究评估了提出的技术在22个软件开发项目中的实施情况。所提出的技术已被应用于实际项目中,目的是评估与传统技术相比的准确性和变异性。进行了具有95%显着性水平的假设检验,所提出的技术比传统的计算成本效益指数(CPI)和竣工估算(EAC)的技术更为准确和精确。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号