Cost Progress and Earned Value Analysis with Stochastic Activity Durations and Costs in Project Scheduling Problems

机译:随机活动持续时间和项目调度问题的成本进展和赚取的价值分析

获取原文

摘要

This paper addressed two key issues: firstly, the cost incurred to complete an activity depends on its random duration; secondly, multiple methods to account for an activity cost are introduced. The upper and the lower bounds for cumulative cost curves over time can be tracked along a project progressed, which is obtained by mixing Monte Carl sampling with Gantt chart analysis. Moreover, these two bounds statistically represent the range for the budget cost of work scheduled; thus, the uncertain earned value analysis (EVA) is probed in our investigation. The conclusions indicate that project managers can obtain a degree of flexibility when adopting uncertain EVA to monitor status during project execution, which differs greatly from deterministic situations. Our study aims to illuminate some insights for the application of EVA under uncertain environments.
机译:本文涉及两个关键问题:首先,完成活动的成本取决于其随机持续时间;其次,引入了多种解释活动成本的方法。累积成本曲线的上限和下界随着时间的推移,通过将蒙特卡尔采样与甘特图分析混合来获得。此外,这两个界限统计地代表了预算的预算成本的范围;因此,在我们的调查中探讨了不确定的赚取的价值分析(EVA)。结论表明,项目经理在采用不确定的EVA时可以获得一定程度的灵活性,以监测项目执行期间的状态,这与确定性情况不同。我们的研究旨在照亮在不确定环境下应用EVA的一些见解。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号