A Rule-Based Approach for Fuzzy Overhaul Scheduling

机译:基于规则的模糊大修调度方法

获取原文
获取原文并翻译 | 示例

摘要

Decisions on an overhaul schedule are often required by a dredging company in Shanghai because the fleet of dredges require regularly maintenance due to their heavy duty work. The decision on an overhaul schedule attempts to determine how the overhaul project completion time can be minimized. However, there are a number of constraints where jobs in the overhaul project have precedence relations, and human resources are limited. In addition, job duration times are fuzzy, and jobs may have several performance modes. Because of the complexity of computation, any exact approaches may be not viable. This paper proposes a fuzzy rule-based heuristic approach using the information available in the system. The approach developed here provides a fast scheduling result in such a complex decision, aiding readjustment of production in time. In addition, the approach also helps the company to save significant costs annually in decisions on overhaul projects.
机译:上海的一家挖泥公司经常需要大修时间表的决定,因为挖泥船队由于工作量大而需要定期维护。大修时间表的决定试图确定如何最大程度缩短大修项目的完成时间。但是,存在许多约束条件,大修项目中的工作具有优先关系,并且人力资源有限。另外,作业持续时间是模糊的,并且作业可能具有几种性能模式。由于计算的复杂性,任何精确的方法可能都不可行。本文利用系统中可用的信息提出了一种基于模糊规则的启发式方法。此处开发的方法可在如此复杂的决策中提供快速的调度结果,有助于及时进行生产调整。此外,该方法还可以帮助公司每年在大修项目决策中节省大量成本。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号