Development of clinical trials in a cooperative group setting: the eastern cooperative oncology group.

机译:在合作小组中开展临床试验:东部合作肿瘤小组。

获取原文
获取原文并翻译 | 示例
           

摘要

PURPOSE: We examine the processes and document the calendar time required to activate phase II and III clinical trials by an oncology group: the Eastern Cooperative Oncology Group (ECOG). Methods: Setup steps were documented by (a) interviewing ECOG headquarters and statistical center staff, and committee chairs, (b) reviewing standard operating procedure manuals, and (c) inspecting study records, documents, and e-mails to identify additional steps. Calendar time was collected for each major process for each study in this set. RESULTS: Twenty-eight phase III studies were activated by ECOG during the January 2000 to July 2006 study period. We examined a sample from 16 of those studies in detail. More than 481 distinct processes were required for study activation: 420 working steps, 61 major decision points, 26 processing loops, and 13 stopping points. Median calendar days to activate a trial in the phase III subset was 783 days (range, 285-1,542 days) from executive approval and 808 days (range, 435-1,604 days) from initial conception of the study. Data were collected for all phase II and phase III trials activated and completed during this time period (n = 52) for which development time represented 43.9% and 54.1% of the total trial time, respectively. CONCLUSION: The steps required to develop and activate a clinical trial may require as much or more time than the actual completion of a trial. The data shows that to improve the activation process, research should to be directed toward streamlining both internal and external groups and processes.
机译:目的:我们检查一个肿瘤学小组:东部合作肿瘤学小组(ECOG),以激活该过程并记录启动II和III期临床试验所需的日历时间。方法:通过以下方式记录设置步骤:(a)采访ECOG总部和统计中心的工作人员以及委员会主席,(b)审查标准操作程序手册,以及(c)检查研究记录,文档和电子邮件以识别其他步骤。在该组研究中,为每个主要过程收集了日历时间。结果:ECOG在2000年1月至2006年7月的研究期内启动了28项III期研究。我们详细研究了其中16项研究的样本。激活研究需要超过481个不同的过程:420个工作步骤,61个主要决策点,26个处理循环和13个停止点。在第三阶段亚组中启动试验的中位数天数是,从行政批准开始算起783天(范围为285-1542天),而从最初研究开始算起为808天(范围为435-1604天)。收集了在此期间(n = 52)激活和完成的所有所有II期和III期试验的数据,其开发时间分别占总试验时间的43.9%和54.1%。结论:开展和启动临床试验所需的步骤可能需要比实际完成试验更多或更多的时间。数据表明,为了改善激活过程,研究应针对简化内部和外部小组与过程。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号