PJM Interconnection and transmission owners within its footprint lastrnweek asked the US Federal Energy Regulatory Commission to deny anrnemergency motion that they argued would effectively stay an Aprilrnorder allocating costs for the Bergen-Linden Corridor regionalrntransmission upgrade project.rnThe emergency motion filed by General Electric subsidiary LindenrnVFT May 24 sought some form of rate relief — suggesting a number ofrnways the commission could halt the imposition of the project's costsrnon Linden — and the initiation of hearing and settlement judgernprocedures on the significant changes PJM made to the project's costrnresponsibility assignments in a February 8 filing (ER17-950).