...
首页> 外文期刊>Nuclear news >Outage work at FPL Group's nuclear power plants
【24h】

Outage work at FPL Group's nuclear power plants

机译:FPL集团核电厂的停工

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

Turkey Point-3 had its reactor vessel head replaced last year. Other FPL Group units have the same job planned for the near future. With The Completion Of the Turkey Point-3 outage last December, FPL Group's nuclear fleet achieved a milestone in replacing the first of four reactor vessel heads. A company subsidiary, Florida Power and Light Company, operates four plants—St. Lucie-1 and -2 and Turkey Point-3 and -4—while another subsidiary, FPL Energy, operates the Seabrook plant. This year, Turkey Point-4 and St. Lucie-1 will go through the process of replacing their reactor vessel heads. St. Lucie-1 will also replace its pressurizer during the same outage. St. Lucie-2 will wait until 2007 to replace its reactor head and steam generators.
机译:土耳其Point-3去年更换了反应堆船头。 FPL集团的其他部门在不久的将来计划完成相同的工作。去年12月,随着“土耳其Point-3”事故的完成,FPL集团的核舰队在更换四个反应堆船头中的第一个上达到了一个里程碑。公司子公司Florida Power and Light Company运营着四个工厂,分别是St. Lucie-1和-2和Turkey Point-3和-4-另一家子公司FPL Energy经营Seabrook工厂。今年,Turkey Point-4和St. Lucie-1将经历更换反应堆船头的过程。在同一次停机期间,圣露西1号还将更换其增压器。圣露西2号将等到2007年更换其反应堆头和蒸汽发生器。

著录项

  • 来源
    《Nuclear news》 |2005年第4期|p.42-44|共3页
  • 作者

  • 作者单位
  • 收录信息
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类 原子能技术;
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号