SCHEDULING OF NUCLEAR POWER PLANT OUTAGES AND WORK DURING AN OUTAGE - A REVIEW

机译:停电期间核电厂房中断与工作的安排 - 评论

获取原文

摘要

A Nuclear Power Plant (NPP) outage is a planned period of time during which the plant does notproduce energy and undergoes offline refueling and maintenance. For a commercial power plant, anoutage window could last up to two months during which thousands of activities are performed. Theseactivities are related by precedence thereby constituting an activity network. A team of planners/schedulersdevelops an outage schedule at least a year in advance of the execution of an outage. A significant lossof revenue incurs for every extra outage day beyond the planned period. The four scheduling problemsthat are typically faced in outage scheduling and planning include: (1) selection of outage window for acollection of NPPs, (2) generation of a feasible initial outage schedule, (3) updating the outage schedulewhen unplanned activities arise, and (4) measuring the risk of a given outage schedule. In this paper, wepresent approaches for each of these problems as well as highlight the areas for potential future research.Outage activity networks with both deterministic and stochastic durations are considered.
机译:核电厂(NPP)中断是植物没有的计划时间生产能量并进行离线加油和维护。对于商业电厂,一个中断窗口可能持续长达两个月,在此期间进行数千项活动。这些活动是由最优先相关的,从而构成活动网络。策划者/调度员团队在执行中断之前至少一年开发中断时间表。大幅损失在计划期内的每一个额外停电日都会受到收入。四个调度问题通常面临中断调度和规划,包括:(1)选择中断窗口NPPS的集合,(2)生成可行的初始中断计划,(3)更新中断时间表当未计划的活动产生时,(4)测量给定的中断计划的风险。在本文中,我们对这些问题的每种方法以及突出潜在未来研究的领域。考虑了具有确定性和随机持续时间的中断活动网络。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号