A case study on failure of a tunnel intake

机译:隧道入水口故障的案例研究

获取原文
           

摘要

This paper deals with the study of causes of failure of a tunnel during excavation and the design of pre-support system for proceeding the tunneling. The tunnel, 3396m long, driven by full face method, encountered a failure at the intake during the course of tunneling. Soil tests were carried out to identify the type of soil. The most probable reason for the failure was identified .A pre-support system known as pipe roofing or umbrella arch method was suggested to recover from failure and for proceeding the tunneling. It was modelled using Creo Parametric 1.0 and analysed using ANSYS 12.0 software. This paper concludes that pipe roofing is a practically feasible pre-supporting technique recommended at the site for carrying out further excavation by means of conventional method of tunneling.
机译:本文研究了隧道开挖过程中的破坏原因,以及进行隧道掘进的预支护系统的设计。该隧道全长3396m,采用全断面法驱动,在隧道施工过程中入口发生故障。进行了土壤测试以识别土壤类型。确定了最可能的故障原因。建议使用称为管棚或伞拱方法的预支撑系统,以从故障中恢复并进行隧道施工。它使用Creo Parametric 1.0建模,并使用ANSYS 12.0软件进行分析。本文得出的结论是,管棚是在现场推荐的一种实用可行的预支护技术,用于通过传统的掘进方法进行进一步的开挖。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号