An approximation of the activity duration distribution in PERT

机译:PERT中活动持续时间分布的近似值

获取原文
获取原文并翻译 | 示例
           

摘要

PERT is widely used as a tool for managing large-scale projects. The traditional PFRT approach uses the beta distribution as the distribution of activity duration and estimates the mean and the variance of activity duration based on the “pessimistic”, “optimistic” and “most likely” time estimates. Several authors have modified the original three point PERT estimators to improve the accuracy of the estimates. This article proposes new approximations for the mean and the variance of activity based on “pessimistic”, “optimistic” and “most likely” time estimates. By numerical comparison with actual values, the proposal is shown as more accurate than the original PERT estimates and its modifications. Another advantage of the proposed approximation is that it requires no assumptions about the parameters of the beta distribution as in the case of existing ones.
机译:PERT被广泛用作管理大型项目的工具。传统的PFRT方法使用beta分布作为活动持续时间的分布,并根据“悲观”,“乐观”和“最可能”的时间估算来估算活动持续时间的均值和方差。几位作者修改了原始的三点PERT估计量,以提高估计的准确性。本文根据“悲观”,“乐观”和“最有可能”的时间估计为活动的均值和方差提出了新的近似值。通过与实际值进行数值比较,该建议比原始PERT估计及其修改更准确。提议的近似值的另一个优点是,它不需要像现有参数那样假设β分布的参数。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号