The Effects of Different Activity Distributions on Project Duration in PERT Networks

机译:PERT网络中不同活动分布对项目工期的影响

获取原文
           

摘要

The original PERT technique assumes β distribution for the activity durations. The developments of the past decades have partly refuted this concept; and many different distributions have been introduced.In our research, various distributions (uniform, triangular, β) are applied in case of closed large-scale infrastructure projects.In this paper, the possible effects of these distributions on the project duration are investigated. It is shown that the use of different distributions with the same three-point estimation has a smaller effect on the project duration than a 10% difference in the values of the three-point estimation.
机译:原始的PERT技术假设活动持续时间为β分布。过去几十年的发展部分驳斥了这一概念。在我们的研究中,封闭的大型基础设施项目应用了各种分布(均匀,三角形,β)。本文研究了这些分布对项目工期的可能影响。结果表明,与三点估算值的10%差异相比,使用具有相同三点估算的不同分布对项目工期的影响较小。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号