In order to address quality defects of lining voids, cracking or spalling that occur in operating tunnels, and based on the practices of casting concrete by lining jumbos on site, a conventional tunnel lining jumbo is reno⁃vated and new technology is proposed for grouting of the secondary lining with molds . The stubborn void defects ex⁃isting in conventional secondary linings are solved by injecting the micro-expansion retarded mortar, characterized by good workability and early-strengthening, through an embedded RPC pipe, which improves the quality of the tun⁃nel lining and provides a solid support for safe tunnel operation in the future.%针对运营隧道出现衬砌空洞、开裂、掉块等质量病害原因,并结合现场衬砌台车灌注混凝土的实际情况,文章阐述了对传统隧道衬砌台车实施的改造,提出了二次衬砌带模注浆新工艺。通过预埋RPC注浆管并注入高流动性微膨胀早强缓凝充填砂浆,有效解决了传统二次衬砌空洞缺陷整治难的问题,极大地提高了隧道衬砌工程质量,为今后隧道的安全运营提供了可靠保证。