印度尼西亚GRESIK100万吨水泥粉磨站工程由中国中材国际总承包。地基处理、桩基部分的施工由苏州开普岩土工程有限公司承担。本文以该工程荷载较小的建筑结构为例,介绍了采用沉管振动砂石桩对场地淤泥质软弱土地基的处理。结果表明本工程采用砂石桩法处理软弱土地基是安全可行的,可供类似工程设计施工借鉴参考。%The general contract project of Indonesia GRESIK100 million tons of cement grinding station was undertaken by Sinoma In⁃ternational Engineering Co.,Ltd . The Foundation treatment and the construction of the pile foundation is undertaken by Suzhou Kaipu geotechnical Engineering Co.,Ltd. Took the structures which carries small engineering loads as an example, this article introduces the vibration sinking tube gravel pile using for the treatment of ground muddy soft soil foundation. The results show that this project is feasi⁃ble and safe, it can be used for reference in similar engineering design.