首页> 外文学位 >AN ANALYSIS OF THE TWO-MACHINE STATIC, STOCHASTIC FLOWSHOP WITH LINEAR COMPLETION TIME COSTS.
【24h】

AN ANALYSIS OF THE TWO-MACHINE STATIC, STOCHASTIC FLOWSHOP WITH LINEAR COMPLETION TIME COSTS.

机译:具有线性完成时间成本的两机静态,随机流量分析。

获取原文
获取原文并翻译 | 示例

摘要

This study investigated the n-job, two-machine, static flowshop with independent, exponential job processing times and linear completion time or penalty costs. The objective was to find a job sequence which minimizes the expected total penalty cost for all the jobs. This performance measure is more complicated and more complete than that used in all the previous analytical, stochastic, multi-machine, flowshop studies; namely, the expected schedule length. The expected total penalty cost for all the jobs is a function of both the penalty cost associated with each job and the expected job completion time.;The common assumptions made in most of the static, stochastic, multi-machine, flowshop literature were also made in this research. The general approach utilized in this analysis was a comparison of two job sequences in which the first job sequence is the same as the second except that exactly two adjacent jobs i and j have been interchanged. The job sequence with the lower expected total penalty cost for all the jobs is the preferred job sequence.;We developed in this study seven major results (seven theorems). First, it was shown that the job sequence which minimizes the expected total penalty cost for all the jobs is a permutation schedule. Second, for the two-job case, a necessary and sufficient condition was derived for determining the optimal job sequence. Third, for the n-job case, three sufficient conditions were deduced for job i to precede job j. The first condition turned out to be Rothkopf's Rule (1966), while the third condition is the rule developed by Cunningham and Dutta (1973) for minimizing the expected schedule length.;To specify a complete and optimal job sequence for the n-job case, it was necessary to establish that the three sufficient conditions are transitive. Establishing transitivity was the fourth major result of this study.;On the other hand, the expected schedule length depends only on the expected job completion times. This may be a significant shortcoming, since in many flowshops penalty or holding costs may be considered important.;Fifth, three special cases of the general n-job problem were analyzed. In the first special case studied, we assumed some of the jobs have the same expected processing time on each machine. Both a necessary and sufficient, as well as transitive, condition was derived for job i to precede job j. We assumed in the second special case examined that some jobs have the same expected processing time on the first machine. Two sufficient and transitive conditions were deduced for job i and precede job j. In the third special case investigated, we assumed that k(,il) (GREATERTHEQ) k(,jl) + k(,i2) for jobs i and j, where k(,il), k(,jl), and k(,i2) are the parameters of the exponential processing time distributions for job i on machine one, job j on machine one, and job i on machine two, respectively. One sufficient and transitive condition was derived for job i to precede job j. In each of these special cases, the first condition developed for job i to precede job j is Rothkopf's Rule (1966).;The results imply that jobs with relatively high penalty cost and relatively long expected processing times will tend to be sequenced before jobs with relatively low penalty cost and relatively long expected processing times.
机译:这项研究调查了具有独立的指数作业处理时间和线性完成时间或惩罚成本的n作业,两机静态流程。目的是找到一个工作顺序,使所有工作的预期总罚款成本最小化。与以前的所有分析,随机,多机,流水车间研究中所使用的方法相比,这种性能方法更加复杂和完整。即预期的时间表长度。所有工作的预期总罚款成本是与每个工作相关的罚款成本和预期工作完成时间的函数。;在大多数静态,随机,多机,流水作业文献中也做出了共同的假设在这项研究中。此分析中使用的一般方法是比较两个作业序列,其中第一个作业序列与第二个作业序列相同,只是恰好两个相邻的作业i和j已互换。所有工作的预期总惩罚成本较低的工作序列是首选的工作序列。;在本研究中,我们开发了七个主要结果(七个定理)。首先,表明将所有工作的预期总惩罚成本最小化的工作顺序是排列时间表。其次,对于两份工作的情况,得出了确定最佳工作顺序的必要和充分条件。第三,对于n职位的情况,推论出三个充分的条件,以使工作i优先于工作j。第一个条件证明是Rothkopf的规则(1966),而第三个条件是Cunningham和Dutta(1973)为最小化预期的计划长度而开发的规则;为n个职位指定完整和最佳的工作顺序,因此必须确定这三个充分条件是可传递的。建立可传递性是该研究的第四项主要结果。另一方面,预期的计划长度仅取决于预期的工作完成时间。这可能是一个重大的缺点,因为在许多流水车间中,罚款或持有成本可能被认为很重要。第五,分析了一般n职位问题的三种特殊情况。在研究的第一个特殊情况下,我们假设某些作业在每台机器上具有相同的预期处理时间。得出了作业i优先于作业j的充要条件。在第二个特殊情况下,我们假设在第一台机器上某些作业具有相同的预期处理时间。推导了作业i和作业j之前的两个充分和传递条件。在研究的第三个特殊情况下,我们假设作业i和j为k(,il)(GREATERTHEQ)k(,jl)+ k(,i2),其中k(,il),k(,jl)和k (,i2)分别是机器1上的作业i,机器1上的作业j和机器2上的作业i的指数处理时间分布的参数。推导了作业i优先于作业j的充分和传递条件。在每种特殊情况下,为工作i优先于工作j的第一个条件是Rothkopf的规则(1966).;结果表明,惩罚成本相对较高且预期处理时间相对较长的工作将倾向于在工作i之前进行排序。较低的罚款成本和相对较长的预期处理时间。

著录项

  • 作者

    FORST, FRANK GREGORY.;

  • 作者单位

    University of Illinois at Urbana-Champaign.;

  • 授予单位 University of Illinois at Urbana-Champaign.;
  • 学科 Business Administration General.
  • 学位 Ph.D.
  • 年度 1981
  • 页码 115 p.
  • 总页数 115
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号