High-Risk Tunnel Construction Technology-Research and Practice of Energy Release and Pressure Reduction Technology for High Pressure Watery Karst Tunnel

机译:高风险隧道施工技术-高压水溶岩溶隧道泄压降压技术的研究与实践

获取原文

摘要

In tunnel construction, adverse geological conditions such as lava cave, faultage, high ground stress and harmful gas are often encountered. In karst regions, large high pressure watery filling lava caves bring about extremely high risks to tunnel construction. It is difficult to guarantee safety in construction by dealing with high pressure watery filling lava caves with grouting method. In the practice of YichangWanzhou Railway, an 'energy release and pressure reduction method' is proposed, which has been applied successfully in four HP watery filling lava cave tunnels, including Yunwushan Tunnel. In this paper, Yun-wushan Tunnel is taken as an example for the discussions about the concept, contents, applicable conditions, opportunities and construction procedures of 'energy release and pressure reduction method'.
机译:在隧道施工中,经常遇到不利的地质条件,例如熔岩洞,断层,高地应力和有害气体。在喀斯特地区,巨大的高压含水充填熔岩洞穴会给隧道建设带来极大的风险。通过注浆法处理高压含水充填熔岩洞穴很难保证施工安全。在宜昌万州铁路的实践中,提出了一种“能量释放减压法”,该方法已成功应用于云雾山隧道等4条高压注水熔岩溶洞隧道。本文以云雾山隧道为例,对“降压降压法”的概念,内容,适用条件,机遇和建设程序进行了讨论。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号