This paper presents case histories of five below-ground rescues of tunnel boring machinesrn(TBM), microtunnel boring machines (MTBM) and horizontal directional drilling (HDD) using groundrnfreezing as the primary technology. In all five cases, the tunnel machines/casing became stuck and the tunnelingrncontractors had been unable to fix or retrieve the machines/casing. The case histories include:rn• A 5' diameter MTBM stuck 10 feet from the receiving shaft in Los Angeles, CArn• A 3' diameter MTBM stuck 30 feet deep between a river and an airport runway in Renton, WArn• A 17' diameter TBM stuck 300 feet below a residential area in Lake Forest Park, WArn• A 3' diameter HDD pull-head stuck 65 feet beneath an interstate off-ramp in Marysville, WArn• An 18' diameter TBM stuck inside a broken, leaking portal 90 feet deep in Newark, CArnGround freezing was used on all five projects to create a stable access to either repair or replace the tunnelingrnequipment. Most of the freezing was accomplished with small, cost-effective freeze equipment usingrnchilled calcium chloride brine pumped through either vertical, horizontal or angled steel freeze pipes. Two ofrnthe projects also involved the use of liquid nitrogen in addition to calcium chloride brine. Freeze pipes wererninstalled from ground surface, from inside the access shaft, and from inside the tunnel. In all cases, a solid massrnof frozen soil was created around, above and below the TBM/MTBM/HDD in sandy and silty, unstable soilsrnwith high groundwater conditions. In one case, the pressure on the frozen soil shoring was well over 5 barsrn(70 psi). The five rescue projects were all successful—the contractors were able to complete the tunnels andrnthe project. An overview regarding the basic engineering design, construction difficulties and the final groundrnfreezing solution is presented for each case history.
机译:本文介绍了以冻结法为主要技术的隧道掘进机(TBM),微隧道掘进机(MTBM)和水平定向钻探(HDD)的五种地下救援案例。在所有五种情况下,隧道机械/套管都卡住了,隧道承包商无法修复或收回机械/套管。案例历史包括:rn•直径5'的MTBM距加利福尼亚州洛杉矶的接收井10英尺处卡死•直径3'的MTBM距河与华盛顿州伦顿的机场跑道之间的深30英尺处卡住•直径17' TBM卡在华盛顿州森林湖公园的居民区下方300英尺处•3英寸直径的HDD拉头卡在华盛顿州马里斯维尔的州际匝道下方65英尺处•18英寸直径的TBM卡在破碎的,泄漏的入口内90在五个项目中都使用CArnGround冻结技术在纽瓦克(Newark)的一英尺深处创建了一个稳定的通道,以维修或更换隧道设备。大多数冷冻是使用小型,经济高效的冷冻设备完成的,该设备使用通过垂直,水平或成角度的钢制冷冻管泵送的冷冻氯化钙盐水。该项目中的两个还涉及除氯化钙盐水外还使用液氮。冻结管是从地面,检修井内部和隧道内部安装的。在所有情况下,在地下水条件高的沙质粉质,不稳定土壤中,在TBM / MTBM / HDD周围,上方和下方均会形成固态的冻土。在一种情况下,冻土支撑的压力远远超过5 barrn(70 psi)。五个救援项目均获得了成功,承包商得以完成了隧道并完成了该项目。针对每个案例历史记录,概述了基本的工程设计,施工困难和最终的地面冻结解决方案。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号