首页> 外文会议>International Conference on Sustainable Design, Engineering and Construction >Using PIPS to minimize causes of delay in Saudi Arabian construction projects: university case study
【24h】

Using PIPS to minimize causes of delay in Saudi Arabian construction projects: university case study

机译:利用PIPS最大限度地减少沙特阿拉伯建设项目延迟原因:大学案例研究

获取原文

摘要

Saudi Arabia has been facing issues with completing construction projects on time and on budget. It has been documented that 70% of public construction projects are delayed. A case study was performed at a University campus in northern Saudi Arabia, identifying the major causes of project delays. The University was experiencing delays from 50% to 150%. The delay factors were gathered from the University Projects Director. The University's delay factors were then compared to delay factors experienced on Saudi construction projects, identified by performing a literature research. The comparison identified nine causes of delays that both studies documented. The study also proposes a solution to minimize the nine major delay factors. A literature research identified one construction management method, the Performance Information Procurement System (PIPS), has documented multiple times its ability to improve project performance and minimize delays.
机译:沙特阿拉伯一直面临着按时和预算完成建设项目的问题。已记录70%的公共建筑项目延迟。在沙特阿拉伯北部大学校园进行了一个案例研究,确定了项目延误的主要原因。该大学经历了50%至150%的延误。延迟因素从大学项目总监收集。然后将大学的延迟因素与沙特建设项目经历的延迟因素进行比较,通过进行文献研究确定。比较确定了两个研究记录的延迟的九个原因。该研究还提出了一种最小化九个主要延迟因素的解决方案。文献研究确定了一个建筑管理方法,性能信息采购系统(PIPS),已经记录了其提高项目性能并最大限度地减少延迟的能力多次。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号