Delays in construction projects - causes and impacts

机译:建设项目的延误-原因和影响

获取原文

摘要

The main aim of this paper is to identify the main causes for the delays in the Portuguese construction industry and its impact, with the purpose of increasing knowledge on the causes and impacts of delays in construction projects. The Relative Importance Index was adopted to classify the importance of the 47 causes and six impacts identified causes of delays. Results show the main causes of delay are slow decision-making, changes to orders, unrealistic timescales and poor contract specifications, financial constraints on the contractor and the type of bidding and contract award process. The main impacts are time and cost overruns and disputes. Factor analysis revealed eight high-level causes that result in 26 of the original causes. Finally, Pearson correlation coefficients were calculated to find the relationship between the extracted factors (latent causes) and impacts, revealing that lack of commitment and substandard contracts are positively correlated with all impacts, and poor consultant performance is negatively correlated with time overrun. These findings are expected to improve the scientific community's knowledge of construction management.
机译:本文的主要目的是找出造成葡萄牙建筑业延误的主要原因及其影响,目的是增加对建筑项目延误的原因和影响的认识。通过了相对重要性指数来对47个原因的重要性进行分类,并确定了6个影响来确定延误原因。结果表明,延迟的主要原因是决策缓慢,订单变更,时间表不切实际和合同规格不佳,承包商的财务约束以及招标和合同授予过程的类型。主要影响是时间和成本超支以及纠纷。因子分析显示了8个高级原因,这些原因导致了26个原始原因。最后,计算了Pearson相关系数以找出提取的因素(潜在原因)与影响之间的关系,这表明缺乏承诺和不合标准的合同与所有影响均呈正相关,而顾问绩效不佳与时间超支则呈负相关。这些发现有望提高科学界对施工管理的认识。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号