TRANSPORTING A TBM THROUGH A LARGE CITY ON THE EAST SIDE CSO TUNNEL PROJECT IN PORTLAND, OREGON

机译:在俄勒冈州波特兰东侧CSO隧道项目的一个大城市运输TBM

获取原文

摘要

Upon completion of the 20,340-lf (6,200-m) North Tunnel drive for the Portland East Side Combined Sewer Overflow Tunnel Project in Portland, Oregon, the slurry tunnel boring machine (TBM) had to be returned from the Port Center shaft at Swan Island to the Opera shaft at the main mining site for the 8,860-lf (2,700-m) South Tunnel drive. At Port Center shaft, the main 565-ton TBM and TBM tail shield were hoisted out of the shaft in two pieces using four 220-ton strand jacks mounted on a 700-ton hydraulic boom gantry system supported by Emmert International’s custom gantry tracks designed to span the shaft. After lifting the TBM components out of the shaft, the gantry system loaded the TBM components onto two Goldhofer platform trailers, which then transported the TBM and tail shield to a barge utilizing a roll-on/roll-off method. The barge transported the TBM and tail shield up the Willamette River back to the Opera shaft site where the process was repeated in reverse for re-installation of the TBM inside Opera shaft. This paper discusses the considerations for selecting the means of transportation, the engineering and planning of the TBM transport, and the lessons learned from this successful operation.
机译:在完成20,340-LF(6,200米)北隧道驱动器的波特兰东侧联合下水道溢流隧道项目,俄勒冈州波特兰,泥浆隧道镗床(TBM)必须从港口中心轴返回天鹅岛在主矿工的歌剧轴上为8,860-LF(2,700米)南隧道驱动。在端口中心轴上,使用由Emmert International的定制龙门轨道的700吨液压龙门龙门架系统上安装在两块220吨股线架中,将主要的565吨TBM和TBM尾部屏蔽从轴上悬挂在两个件中。跨越轴。将TBM部件从轴提升后,龙门系统将TBM部件装入两个Goldhofer平台拖车上,然后使用滚动/滚动方法将TBM和尾部屏蔽运输到驳船上。驳船运送了TBM和尾屏蔽威拉米特河回到歌剧轴网站,反向重复该过程以重复于歌剧轴内部的TBM。本文讨论了选择运输工具,TBM运输工具的考虑,以及从这种成功运行中吸取的经验教训。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号