Overnight Pavement Replacement Using Precast Panels and Conventional Subgrade Material Washington Dulles International Airport Case Study

机译:使用预制板和常规路基材料替换过夜的人行道华盛顿杜勒斯国际机场案例研究

获取原文
获取原文并翻译 | 示例

摘要

During a two-week period in October - November 2002, a rapid panel replacement of six panels of rigid airfield pavement was performed at Washington Dulles International Airport, Washington, DC (IAD). The work was performed during the night on active taxilanes and taxiways. The durations of the closures were 15.5, 9.5 and 8.5 hours on each of three replacement nights, showing a steep learning curve is involved. However the project demonstrated the process is viable for use in rapid pavement replacement projects using only nightly closures, enabling immediate reopening of the pavement to aircraft service loads. A special grading machine was used to create an accurate bearing surface in a compacted layer of granular subgrade material. The grading and precasting processes can produce planar surfaces or warped, fully three-dimensional surfaces. This project required warping. Panels were uniform in thickness but deviated from a true plane by as much as 40 mm (1-9/16") vertically. Panels were placed within 6 mm (1/4") on the vertical axis and had a 6 mm (1/4") maximum placement deviation laterally. The new panels are expected to have a minimum service life of five years. Though the precast panels are likely to survive longer, surrounding original pavement is expected to continue to deteriorate, requiring replacement after five years. Although the project at IAD involved a total of six panels replaced two at a time, the technique can be applied to smaller scale projects or expanded over several months to replace hundreds or thousands of panels. With the technology's history on highways plus the success of the IAD project, the rapid panel replacement process shows promise for important new applications such as reconstruction of taxiways using only night closures, or replacement of a critical access Taxiway over a weekend.
机译:在2002年10月至2002年11月的两周时间内,在华盛顿特区的华盛顿杜勒斯国际机场(IAD)快速更换了六块刚性飞机场路面。这项工作是在夜间在活跃的滑行道和滑行道上进行的。在三个替换夜晚中,每个关闭的持续时间分别为15.5、9.5和8.5小时,显示涉及陡峭的学习曲线。但是,该项目证明了该方法可用于仅需每晚关闭的快速人行道更换项目中,从而可以立即将人行道重新开放至飞机服务负荷。使用一台特殊的平地机在压实的粒状路基材料层中创建准确的支承面。分级和预制过程可以产生平坦的表面或扭曲的,完全三维的表面。该项目需要翘曲。面板厚度均匀,但垂直方向偏离真实平面最多40毫米(1-9 / 16英寸)。面板垂直轴放置在6毫米(1/4英寸)以内,而厚度为6毫米(1英寸) / 4“)最大横向偏移。新面板的最小使用寿命预计为五年。尽管预制面板的使用寿命可能更长,但周围的原始铺面预计会继续恶化,需要在五年后更换。尽管IAD的项目总共涉及六个面板,一次只能更换两个面板,但该技术可以应用于规模较小的项目,也可以在几个月内扩展以替换成百上千的面板。在IAD项目中,快速更换面板过程显示出有望用于重要的新应用,例如仅使用夜间关闭装置来重新构建滑行道,或者在周末更换重要的进入滑行道。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号