Overnight Pavement Replacement Using Precast Panels and Conventional Subgrade Material Washington Dulles International Airport Case Study

机译:使用预制面板和传统的路基材料华盛顿杜勒斯国际机场案例研究更换过夜

获取原文

摘要

During a two-week period in October -November 2002, a rapid panel replacement of six panels of rigid airfield pavement was performed at Washington Dulles International Airport, Washington, DC (IAD). The work was performed during the night on active taxilanes and taxiways. The durations of the closures were 15.5, 9.5 and 8.5 hours on each of three replacement nights, showing a steep learning curve is involved. However the project demonstrated the process is viable for use in rapid pavement replacement projects using only nightly closures, enabling immediate reopening of the pavement to aircraft service loads. A special grading machine was used to create an accurate bearing surface in a compacted layer of granular subgrade material. The grading and precasting processes can produce planar surfaces or warped, fully three-dimensional surfaces. This project required warping. Panels were uniform in thickness but deviated from a true plane by as much as 40 mm (1-9/16") vertically. Panels were placed within 6 mm (1/4") on the vertical axis and had a 6 mm (1/4") maximum placement deviation laterally. The new panels are expected to have a minimum service life of five years. Though the precast panels are likely to survive longer, surrounding original pavement is expected to continue to deteriorate, requiring replacement after five years. Although the project at IAD involved a total of six panels replaced two at a time, the technique can be applied to smaller scale projects or expanded over several months to replace hundreds or thousands of panels. With the technology's history on highways plus the success of the IAD project, the rapid panel replacement process shows promise for important new applications such as reconstruction of taxiways using only night closures, or replacement of a critical access Taxiway over a weekend.
机译:在10月份的两周期 - 在2002年10月期间,在华盛顿杜勒斯国际机场,华盛顿特区(IAD)中,在华盛顿杜勒斯国际机场进行了六面板的快速面板更换了六个刚性机场路面。这项工作是在积极的卡车和滑行道上的夜晚进行。三个更换夜晚的封闭持续时间为15.5,9.5和8.5小时,显示涉及陡峭的学习曲线。然而,该项目证明了该过程可用于仅使用夜间封闭的快速路面更换项目,可以立即将路面重新开放到飞机服务负荷。使用特殊的分级机器在压实的粒状路基材料层中产生精确的轴承表面。分级和预留过程可以产生平面表面或翘曲,完全三维表面。这个项目需要翘曲。面板的厚度均匀,但垂直偏离真正的平面(1-9 / 16“)。将面板放在垂直轴上的6毫米(1/4”)内,并具有6毫米(1 / 4“)横向放置偏差。预计新面板将拥有五年的最低使用寿命。虽然预制面板可能会更长时间,但围绕原始路面预计将继续恶化,需要五年后更换。虽然IAD的项目一次涉及两组六个面板一次,但该技术可以应用于较小的规模项目或扩展几个月,以取代数百或数千个面板。在高速公路上有了技术的历史加上IAD项目,快速面板更换过程显示了重要的新应用,例如仅使用夜间关闭的超级出租车,或者在周末替换关键进入滑行道。

著录项

相似文献

  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号