首页> 外国专利> PACKER TYPE CONTINUOS UNDERGROUND WALL COUPLING AND METHOD OF EXECUTING COUPLING PART THEREBY

PACKER TYPE CONTINUOS UNDERGROUND WALL COUPLING AND METHOD OF EXECUTING COUPLING PART THEREBY

机译:垫圈式连续地下壁联轴器及其执行方法

摘要

PROBLEM TO BE SOLVED: To perform the placement of site placing concrete positively by setting packer mortar placing pipes on either surface of an H-steel having connection members to be connected with coupling parts on the flange ends, securing packer-sheet attachment members on both the ends of the flanges, fastening the packer-sheets thereon in a bag-shaped fashion, and forming placing control communication pipes within the flanges. ;SOLUTION: A continuos packer-type ground wall joint J is connected to the coupling part of a box-type steel sheet pile via connection parts 11 to subsequently be built in an earth excavation ditch by a crane. Next, while controlling the top end by pipings 17, continuous placement of mortar is implemented by a pump in the ground from packer mortar placing pipings 13 via pouring pipes. Then, the placement pipings 13 are pulled up in accordance with the placement situation and cut by its upper part. Placement is executed to the top end so that placement is completed to the coupling parts. Mortar serves to push and expand the packer sheets 16 in order that concealment is done in conformity with the ground configuration of an earth excavation ditch. Thus, placement of site placing concrete can be effected positively.;COPYRIGHT: (C)1998,JPO
机译:解决的问题:通过在H型钢的任一表面上放置封隔器砂浆放置管,并在法兰端部上与联接部件相连接,将封隔器砂浆放置管固定,从而可靠地进行现场浇筑混凝土的放置,同时将封隔器板连接件固定在两者上法兰的两端,以袋状方式将封隔器板紧固在其上,并在法兰内形成放置控制连通管的步骤。解决方案:连续式封隔器式地下墙缝J通过连接部件11连接到箱式钢板桩的连接部件,随后用起重机将其安装在开挖沟中。接下来,在通过管道17控制顶端的同时,通过泵从地下封隔器灰浆放置管道13经由浇注管将灰浆连续地放置在地面中。然后,根据放置情况将放置管道13上拉并通过其上部切割。在顶端执行贴装,从而完成对耦合零件的贴装。砂浆用于推动和扩展封隔器板16,以便根据挖土沟渠的地面构造进行隐藏。因此,可以积极地进行现场浇筑混凝土的浇筑。;版权所有:(C)1998,日本特许厅

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号