RAPID REPLACEMENT METHOD AND APPARATUS USING PULLING-UP FACILITY AND SCAFFOLD TRUSS WITH WHEELS UNDER THE BOTTOM OF EXISTING AND REPLACING BRIDGES
RAPID REPLACEMENT METHOD AND APPARATUS USING PULLING-UP FACILITY AND SCAFFOLD TRUSS WITH WHEELS UNDER THE BOTTOM OF EXISTING AND REPLACING BRIDGES
展开▼
机译:在现有和更换桥梁底面的上拉设备和脚手架桁架的快速更换方法和装置
展开▼
页面导航
摘要
著录项
相似文献
摘要
PURPOSE: A construction method and a construction device for rapidly replacing an upper structure of a bridge using a cable hauling machine, a temporary lifter, and a horizontal moving member are provided to reduce time required for replacing an upper structure of a bridge. CONSTITUTION: A construction method for rapidly replacing an upper structure of a bridge using a cable hauling machine, a temporary lifter, and a horizontal moving member is as follows. Lifting devices(10) are installed in both piers(100). A temporary lifter(20) is installed under a replaced upper structure(1) between the piers. The temporary lifter is ascended by the lifting devices to a position in which a bridge upper structure(3a) can be horizontally moved. The replaced upper structure is drawn to the bridge upper structure and is eliminated on the top of the temporary lifter.
展开▼