[Problem] To easily and precisely predict the amount of a Г phase to be formed in a galvannealed steel sheet. [Solution] A method for predicting the amount of a Г (capital gamma) phase to be formed in the coating layer when producing a galvannealed steel sheet through a hot-dip plating line that includes a hot-dip galvanizing bath immersion zone, a temperature-rising zone, a soaking zone, and a cooling zone in this order, the method comprising using the following equation (1) to predict the total average thickness, ГTOTAL (μm), of the Г phase formed by passing the steel sheet through all the zones. ГTOTAL=V(T0)×(t0-Δt)1/2 (1) In equation (1), V(T0) is the rate of increase in the thickness of the Г phase (μm/sec1/2), t0 is the converted soaking time (sec), and Δt is the retardation time (sec) attributable to a delay in Г-phase formation in the beginning of immersion in the plating bath.
展开▼
机译:[问题]为了容易且准确地预测镀锌钢板中的Г相的生成量。 [解决方案]一种用于预测通过包括热浸镀锌浴浸没区,温度的热浸镀线生产镀锌钢板时在涂层中形成的Г(资本伽马)相的量的方法。上升区,均热区和冷却区的顺序,该方法包括使用以下等式(1)预测Г相的总平均厚度Г TOTAL Sub>(μm)通过使钢板穿过所有区域而形成。 Г TOTAL Sub> = V(T 0 Sub>)×(t 0 Sub>-Δt) 1/2 Sup>(1)在式(1),V(T 0 Sub>)是Г相厚度的增加率(μm/ sec 1/2 Sup>),t 0 Sub>是转换后的均热时间(秒),Δt是归因于浸入镀液开始时Г相形成延迟的延迟时间(秒)。
展开▼