PROBLEM TO BE SOLVED: To enhance removal efficiency of slime that tends to sink to the hole bottom of a drilled hole in a construction method for a cast-in-place concrete pile.;SOLUTION: A tremie pipe 4 is disposed on the inner peripheral side of a steel bar basket 3, and a convection pipe 5 is disposed near a hole wall 2a on the outer peripheral side of the steel bar basket 3. Each of the tip ends is inserted up to a depth in which they reach or approach a hole bottom 2b. Prior to installation of concrete 9 via the tremie pipe 4, stable solution 1 inside or outside a drilled hole 2 is suctioned so that it is discharged from an axis-directional tip of either the convection pipe 5 or the tremie pipe 4, while the stable solution 1 is suctioned from the other one of the axis-directional tips so that it is returned into the drilled hole 2, and slime in the stable solution 1 is removed while the stable solution 1, which is present around the hole bottom 2b of the hole wall 2, is forced to circulate.;SELECTED DRAWING: Figure 1;COPYRIGHT: (C)2018,JPO&INPIT
机译:解决的问题:在现浇混凝土桩的施工方法中,为了提高泥浆的去除效率,该泥浆易于沉到钻孔的孔底;解决方案:解决方案:在内周面上放置一个特雷米管4并且,在钢制筐3的外周侧的孔壁2a的附近,配置有对流管5。孔底2b。在通过特雷米管4安装混凝土9之前,要抽吸钻孔2内部或外部的稳定溶液1,以便将其从对流管5或特雷米管4的轴向顶端排出。从另一个轴向吸头吸取溶液1,使其返回到钻孔2中,并除去稳定溶液1中的粘液,同时在溶液的孔底2b周围存在稳定溶液1。孔壁2被迫流通。;选定的图纸:图1;版权:(C)2018,JPO&INPIT

著录项

相似文献

  • 专利
  • 外文文献
  • 中文文献
获取专利

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号