Formal DEVS modelling and simulation of a flow-shop relocation method without interrupting the production

机译:正式的DEVS建模和流水车间重定位方法的仿真,而不会中断生产

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

This paper presents an organizational method of transfer of a flow-shop to a new site without interrupting the production. This method, which can be used even in case of requirements during the removal period, consists in segmenting the flow-shop removal into successive removals of groups of machines. This method can be successfully applied provided a prime condition is met: there must be sufficient stock upstream of the different groups of machines. The role of these stocks is to ensure continuity of production operations between the old and the new site, while a non-operational group of machines is being removed. The removal of groups of machines goes on until the whole production line is transferred to the new site and operational on this site. To validate this approach, we used a simulation and developed a flow-shop model according to the DEVS formalism. Our model makes it possible to segment a production line. We can therefore simulate a sequential transfer of groups of machines to the new site. The most effective solutions among those proposed suggest starting with the final group of machines (finished products) to finish with the first group. In this paper, we present and discuss some simulation results for an industrial case study. These results demonstrate the compared effectiveness of different removal strategies, and help decide for the appropriate estimated project management.
机译:本文提出了在不中断生产的情况下将流水车间转移到新站点的组织方法。即使在拆卸期间有要求的情况下也可以使用这种方法,该方法包括将流水车间的拆卸分为连续的机器组拆卸。如果满足主要条件,则可以成功应用此方法:在不同的机器组上游必须有足够的库存。这些库存的作用是确保在旧站点和新站点之间进行生产操作的连续性,同时删除一组非运行中的机器。机器组的拆卸将继续进行,直到将整个生产线转移到新站点并在该站点上运行为止。为了验证这种方法,我们使用了仿真,并根据DEVS形式主义开发了流水车间模型。我们的模型使分割生产线成为可能。因此,我们可以模拟将机器组顺序转移到新站点。在提出的建议中,最有效的解决方案建议从最后一组机器(成品)开始,到第一组机器结束。在本文中,我们提出并讨论了一些工业案例研究的仿真结果。这些结果证明了比较不同清除策略的有效性,并有助于决定适当的估计项目管理。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号