...
首页> 外文期刊>Iron & Steel Review >Reduced revamp duration at Chiba No. 6 blast furnace
【24h】

Reduced revamp duration at Chiba No. 6 blast furnace

机译:减少千叶6号高炉的改造时间

获取原文
获取原文并翻译 | 示例
   

获取外文期刊封面封底 >>

       

摘要

In the revamp of the Chiba No.6 blast furnace, a short revamp time of 62 days was achieved, reducing the period required for the conventional method by half. The main techniques employed were:For the dismantling and assembly of the furnace body, a large-block ring method was developed, in which the body was dismantled in large, ring-shaped blocks, and then assembled in a similar manner, using large sections that included the steel shell,staves and auxiliary equipment.In laying the hearth bricks, using large brick blocks reduced the number of bricks by half. An efficient continuous work system was also adopted.With the furnace top equipment, the bunkers were assembled as a single unit outside the supporting columns, while work was performed simultaneously inside the columns. The equipment was installed in large units wherever possible. Work, up to theinstallation of the piping and other auxiliary equipment, was performed in advance.Shop tests were made as complete as possible, to minimize testing in the field. Advance debugging by simulation tests was also completed as far as possible.To remove residual material from the furnace, conditions were created that permitted the efficient use of large equipment.Because the large-block ring method and large hearth bricks were used for the first time in this project, various investigations and experiments were carried out in advance. However, in a review after the revamp was completed, several points forimprovement were still found. In future revamps, attempts will be made to achieve a further reduction in the amount of work.Chiba No. 6 blast furnace was blown in for its second campaign on May 26, 1998, achieved a rapid ramp-up and is now functioning smoothly.
机译:在千叶6号高炉的改造中,改造时间缩短到62天,从而使传统方法所需的时间缩短了一半。所采用的主要技术是:对于炉体的拆卸和组装,开发了一种大块环方法,该方法将炉体分解成大的环形块,然后以类似的方式使用大的截面进行组装。其中包括钢壳,壁板和辅助设备。在铺设炉膛砖时,使用大砖块将砖的数量减少了一半。还采用了有效的连续工作系统。借助炉顶设备,将料仓作为单个单元组装在支撑柱外部,同时在柱内部同时进行工作。尽可能将设备安装在大单元中。直到安装管道和其他辅助设备之前,都已预先进行工作。工厂测试尽可能完整,以最大程度地减少现场测试。还通过模拟试验尽可能地进行了预调试。为去除炉子中的残留材料,创造了可以有效使用大型设备的条件。因为首次使用大块环法和大型炉膛砖在这个项目中,事先进行了各种调查和实验。但是,在改造完成后的一次审查中,仍然发现了几点需要改进的地方。在将来的改型中,将努力进一步减少工作量。千叶6号高炉于1998年5月26日进行了第二次生产活动,并迅速上架,目前运行平稳。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号