THE period from January to March 2003 saw the start of the second Wirth IBM, Brunei, on the down line on Contract 240, the start of the down line Lovat IBM, Judy, on Contract 250 and the first two breakthroughs. However, it also saw the first and only major incident, an unexpected ground settlement, which caused a three-month delay in the up line drive on Contract 240. After the Christmas break the two Kawasaki TBMs for Contract 220 started where they left off before Christmas with the up line increasing it progress each month and achieving its best month in February of 775 m, before breaking through into the Graham Road shaft, after a drive of 3.2 km, on March 12, 2003. A full tool change on the cutterhead of the IBM, along with other refurbishment and maintenance, was carried out. The drive recommenced on March 28, 2003.
机译:从2003年1月到2003年3月,第二个Wirth IBM文莱在合同240的下线启动,第二个Lovat IBM Judy在250号合同的下线启动,并且前两个突破。但是,它也看到了第一个也是唯一的重大事件,意外的地面沉降,这使240号合同的上行驱动延迟了三个月。圣诞节休息后,两个220号合同的川崎TBM开始了停工随着上行线路的增加,圣诞节每个月都有进展,并在2月份达到了775 m的最佳月份,然后在2003年3月12日经过3.2 km的驱动力冲入Graham Road竖井。进行了IBM的更新以及其他翻新和维护。该驱动器于2003年3月28日重新启动。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号