Overhaul maintenance of modern bulldozers with software-based management techniques (PERT/CPM)

机译:使用基于软件的管理技术(PERT / CPM)对现代推土机进行大修维护

获取原文
获取原文并翻译 | 示例

摘要

Software programs on programme evaluation and review techniques (PERT) and critical path method (CPM) techniques have been developed to analyze the major overhauling of modern bulldozers. The knowledge of time and cost involved in a particular repair activity is essential to decide whether to continue the interrupted work and to assess whether or not it is possible to complete field operation within the stipulated time. These techniques identified forty two subsystems or activities. An analytical programme was subsequently worked out for the various operations related to major overhauling of bulldozer. The expected completion of all events required 192 hr with a variance of 8 hr. The analysis revealed that the probability of completing the overhauling ranged from 0.299 to 0.331 for completion duration of 185 to 200 hr respectively. The algorithms developed through software programs for major overhauling of bulldozer proved their superiority in the validation.
机译:已经开发了有关程序评估和审查技术(PERT)和关键路径方法(CPM)技术的软件程序,以分析现代推土机的大修。了解特定维修活动的时间和成本对于决定是否继续中断的工作以及评估是否有可能在规定的时间内完成现场操作至关重要。这些技术确定了42个子系统或活动。随后针对与推土机大修相关的各种操作制定了分析程序。所有事件的预期完成需要192小时,方差为8小时。分析显示,完成时间为185至200 hr时,完成大修的概率分别为0.299至0.331。通过软件程序开发的用于推土机大修的算法证明了它们在验证中的优越性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号