首页> 外文期刊>IEEE Transactions on Power Delivery >Unit commitment of main transformers for electrified mass rapid transit systems
【24h】

Unit commitment of main transformers for electrified mass rapid transit systems

机译:电气化大众快速运输系统主变压器的机组承诺

获取原文
获取原文并翻译 | 示例
           

摘要

This paper proposes the transformer planning for an electrified mass rapid transit (MRT) system so that the overall cost of main transformers is minimized over the life cycle. The unit commitment is applied to derive the optimal transformer capacity to meet the annual peak demand and provide reserve for service reliability. The motion equation of train sets is used to derive the dynamic power consumption and travel distance as each time snapshot. The Simulink package is applied to solve the power demand of each train set by the simulation of VVVF inverters and induction motors. The DC/AC load flow analysis is performed to find the annual power loading of traction substations (TSS) and whole Taipei MRT network. The transformer loss, investment, and service reliability are used to define the equivalent cost of all feasible states for each dynamic programming (DP) stage. According to the computer simulation, very significant cost saving is obtained by the proposed methodology for transformer capacity planning of an MRT network.
机译:本文提出了电动快速公交(MRT)系统的变压器规划,以便在生命周期内将主变压器的总成本降至最低。单位承诺用于得出最佳变压器容量,以满足年度峰值需求并为服务可靠性提供储备。列车组的运动方程式用于在每次快照时得出动态功耗和行驶距离。 Simulink软件包用于通过模拟VVVF逆变器和感应电动机来解决每列火车的功率需求。进行DC / AC潮流分析以找出牵引变电站(TSS)和整个台北捷运网络的年度电力负荷。变压器损耗,投资和服务可靠性用于定义每个动态编程(DP)阶段所有可行状态的等效成本。根据计算机仿真,通过所提出的捷运网络变压器容量规划方法,可以节省大量成本。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号