ONEOK Partners,L.P.has awarded a contract to J7 Contractors for an $80 million natural gas liquids (NGL) pipeline lateral,connecting the Denver-Julesburg Basin in northeastern Colorado with the Overland Pass Pipeline now under construction.rnThe 125-mile D-J Basin Lateral Pipeline is designed to transport up to 55,000 bpd of raw natural gas liquids to the 760-mile Overland Pipeline which has the potential to transport 255,000 bpd.Construction of the 6-12-inch lateral pipeline is under way with start-up scheduled in early 2009.The $110-140 million,150-mile Piceance Basin Lateral Pipeline,connecting the Piceance Basin with Overland Pass Pipeline,is expected to be in service by spring.