首页> 外文期刊>KSCE journal of civil engineering >Schedule Compression in Tunneling Projects by Adjusting Workflow Variability
【24h】

Schedule Compression in Tunneling Projects by Adjusting Workflow Variability

机译:通过调整工作流可变性来计划隧道项目中的压缩

获取原文
获取原文并翻译 | 示例

摘要

Usually, the tunneling operation is on a critical path in road or railroad construction projects. For minimizing project duration, this study identifies feasible work scenarios, builds simulation models for each scenario, and then analyzes the average duration per unit length of driving distance and efficiency of tunneling equipment. The tunnel work face is usually advanced as far as the ground condition allows the intention to finish the work earlier. As the rock type changes, however, the length per cycle advances, and the work cycle time varies accordingly. Therefore, workflow variability occurs. Workflow variability in tunnel construction operations brings with it waiting time for each work crew and results in delays in the work process. This study evaluates the effects of workflow variability and suggests an approach for shortening the duration of tunneling work by adjusting the driving length of each excavation in the case of two parallel tunnels, not a single tunnel.
机译:通常,在公路或铁路建设项目中,隧道作业是在关键路径上进行的。为了最大程度地缩短项目工期,本研究确定了可行的工作方案,为每种方案建立了仿真模型,然后分析了单位行驶距离的平均工期和掘进设备的效率。隧道工作面通常在地面条件允许的情况下提前进行。但是,随着岩石类型的变化,每个周期的长度会增加,工作周期时间也会相应地变化。因此,发生工作流可变性。隧道施工作业中工作流程的变化会给每个工作人员带来等待时间,并导致工作流程的延迟。这项研究评估了工作流程可变性的影响,并提出了一种在两个平行隧道而不是单个隧道的情况下,通过调整每个开挖的驱动长度来缩短隧道施工时间的方法。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号