Insight into pile set-up and load carrying capacity of driven piles

机译:深入了解打入桩的设置和承重能力

获取原文
获取原文并翻译 | 示例
       

摘要

Pile set-up and pile relaxation refer to the time dependent increase and decrease in the load carrying capacity of driven piles respectively. These two phenomena are governed mainly by the dissipation of excess pore pressure. In the case of pile set-up, the initially induced positive pore pressure within the soil mass becomes almost zero after some time, resulting in an increase in effective stress, whereas in the case of pile relaxation, the reduction of initially induced negative pore pressure causes a decrease in effective stress with time. For the safe and economical design of driven piles, a reliable prediction of the variation in pile capacity is essential. The researchers have tried to understand set-up and relaxation in the past, and attempted to predict the variation in pile capacity. This paper presents an insight into the pile set-up and the time dependent increase in load carrying capacity of driven piles along with some details of pile relaxation through a critical review of experimental and mathematical studies reported until recently. The review shows that the most studies are related to the set-up of driven piles because the driven piles are generally used in loose sandy and soft clayey grounds where set-up phenomenon is often observed. Some empirical relationships have been reported to predict set-up, and demonstrated reasonable success in a number of studies. A number of exploration phase field tests offering potential value in predicting setup have been identified. A possibility of estimating pile set-up during design stage with the help of relevant subsurface exploration program is also discussed.
机译:桩的建立和桩的松弛分别是指随时间变化的打入桩的承载能力。这两种现象主要由多余孔隙压力的耗散决定。在设置桩的情况下,土壤中最初引起的正孔隙压力在一段时间后几乎变为零,导致有效应力增加,而在桩松弛的情况下,初始引起的负孔隙压力减小导致有效压力随时间减少。为了安全,经济地设计打入桩,可靠地预测桩容量的变化至关重要。研究人员过去曾尝试了解设置和松弛,并试图预测桩容量的变化。本文通过对直到最近才报道的实验和数学研究进行了回顾,对打桩的设置和随时间增长的驱动桩的承载能力以及桩松弛的一些细节提供了见解。该评论表明,大多数研究都与打桩的设置有关,因为打桩通常用于经常观察到打桩现象的松散沙质和软质粘土地上。据报道,一些经验关系可以预测设置,并在许多研究中显示出合理的成功。已经确定了许多勘探阶段现场测试,这些测试在预测设置方面具有潜在价值。还讨论了在相关的地下勘探计划的帮助下,在设计阶段估算桩架的可能性。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号