The consortium constructing the Belo Monte Dam in the western Amazon Basin must revise its environmental impact assessment for the project, Brazil's First Regional Federal Appeals Court (TRF1) said, upholding its own decision in March, a federal prosecutor involved in the case told Bloomberg BNA. The appeals court, in the capital of Brasilia, ruled for the second time (Case No. 0025999-75.2010.4.01.3900/ PA) because Norte Energia (NESA), the consortium building the $13 billion, 11,283-megawatt dam, appealed the March decision with the same court. The earlier decision ordered the licensing arm of Brazil's Environment Ministry (IBAMA) to require the consortium to revise its environmental assessment to reflect changes in the project (37 INER 515, 4/9/14).
机译:巴西第一联邦上诉法院(TRF1)表示,在亚马逊河西岸建设Belo Monte Dam的财团必须修改其对该项目的环境影响评估,该案的一名联邦检察官告诉彭博社BNA,该财团在3月维持了自己的决定。 。位于巴西利亚首都的上诉法院第二次作出裁定(案号0025999-75.2010.4.01.3900 / PA),因为建设这个耗资130亿美元,11,283兆瓦的大坝的财团Norte Energia(NESA)向法院上诉。 3月同一法院的判决。较早的决定命令巴西环境部(IBAMA)的许可部门要求该财团修改其环境评估,以反映该项目的变化(37 INER 515,4/9/14)。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号