Formulations for hydroelectric energy production with optimality conditions

机译:具有最佳条件的水力发电生产配方

获取原文
获取原文并翻译 | 示例
           

摘要

This paper analyzes the mathematical properties related to the hydro-power generation optimization problem. From the problem's physical nature, it can be concluded that the hydro-power generation is a function of the plant productivity and the water discharge. Since the plant productivity must be an increasing function of the net height, it was shown, under mild conditions, that the resulting generation is a strongly increasing function. Given that, it was established some mathematical properties that guarantee a unique maximum inside the feasible set and, therefore, global optimality. Under this analysis it is possible to derive optimization problems with optimality guarantees. Finally, a problem concerning the minimization of the deficit between supply and demand during a time window for a single power plant is explored. A numerical example based on a real case is given. Other existing formulations could also take advantage of our main results to confirm global optimality or to prove multimodality. These results are also useful to define the best optimization strategies for a given optimization problem.
机译:本文分析了与水力发电优化问题有关的数学性质。从问题的物理性质上可以得出结论,水力发电是工厂生产力和排水量的函数。由于植物的生产力必须是净高度的增加函数,因此表明在温和条件下,最终生成的植物是高度增加的函数。鉴于此,已建立了一些数学属性,这些数学属性可保证可行集内的唯一最大值,从而保证全局最优性。在这种分析下,可以得出具有最优性保证的优化问题。最后,探讨了有关在单个电厂的时间窗口内使供需之间的赤字最小化的问题。给出了基于实际情况的数值示例。其他现有的公式也可以利用我们的主要结果来确认全局最优性或证明多模式性。这些结果对于定义给定优化问题的最佳优化策略也很有用。

著录项

  • 来源
    《Energy Conversion & Management》 |2015年第1期|781-788|共8页
  • 作者单位

    ENACOM Handcrafted Technologies, Rua Jose Vieira de Mendonca 770, 31310-260 Belo Horizonte, Brazil,Graduate Program in Electrical Engineering, Federal University of Minas Gerais, Av. Antonio Carlos 6627, 31270-901 Belo Horizonte, Brazil;

    ENACOM Handcrafted Technologies, Rua Jose Vieira de Mendonca 770, 31310-260 Belo Horizonte, Brazil,Graduate Program in Electrical Engineering, Federal University of Minas Gerais, Av. Antonio Carlos 6627, 31270-901 Belo Horizonte, Brazil;

    ENACOM Handcrafted Technologies, Rua Jose Vieira de Mendonca 770, 31310-260 Belo Horizonte, Brazil,Graduate Program in Electrical Engineering, Federal University of Minas Gerais, Av. Antonio Carlos 6627, 31270-901 Belo Horizonte, Brazil;

    Graduate Program in Electrical Engineering, Federal University of Minas Gerais, Av. Antonio Carlos 6627, 31270-901 Belo Horizonte, Brazil;

  • 收录信息 美国《科学引文索引》(SCI);美国《工程索引》(EI);
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

    Hydropower generation; Self scheduling; Nonlinear programming; Optimality conditions; Pseudo-concavity;

    机译:水力发电;自我调度;非线性编程最优条件;伪凹;