首页> 外文期刊>International Journal of Engineering Research and Applications >Reduction of assembly time in ball valve manufacturing using DMAIC methodology
【24h】

Reduction of assembly time in ball valve manufacturing using DMAIC methodology

机译:使用DMAIC方法减少球阀制造中的装配时间

获取原文
           

摘要

In this present scenario the reduction of cycle time and lead time of a component is essential to uplift the business and to satisfy the customer. The case study was taken in the assembly section of ball valve manufacturing, during the study and observation it was found that more time is consumed to assemble a single ball valve. Hence the DMAIC methodology was applied to investigate the causes to get the solution to overcome it. The various tools and techniques such as SIPOC tool, time study, brain storming, 5S have been applied under DMAIC phases. The reasons are arrived through TIMWOOD method of waste identification and solutions are suggested. The synergic approach of DMAIC and 5S have results a good solution. Finally, the time taken to assemble one ball valve i.e.2.4 min is reduced to 1.8 min and this in turn reduced the lead time of 30 days to 26 days to produce 6000 valves.
机译:在本发明的情况下,组件的循环时间和提前期的减少对于提升业务并满足客户至关重要。在研究和观察期间,在球阀制造的组装部分采取了案例研究,发现更多时间被消耗以组装单个球阀。因此,应用DMAIC方法来调查导致解决方案克服它的原因。在DMAIC阶段施加了各种工具和技术,如SIPOC工具,时间研究,脑撞击,5S。提出了原因,提出了Wimewood方法和解决方案。 DMAIC和5S的协同方法具有良好的解决方案。最后,组装一个球阀I.2.4 min所需的时间减少到1.8分钟,这反过来减少了30天至26天的延长时间,以产生6000阀门。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号