Causes of delay in road construction projects in Malawi

机译:马拉维道路建设项目延误的原因

获取原文
   

获取外文期刊封面封底 >>

       

摘要

A study was conducted to identify the causes of delay in completing road construction projects in Malawi. A literature review was done which yielded 72 typical causes of delay, and a questionnaire was sent to client, contractor and consultant representatives in Malawi. The results were analysed using the Relative Importance Index (RII) and Spearman's Rank Correlation Coefficients, which indicated that the top ten causes of delay in Malawi are: shortage of fuel, insufficient contractor cash-flow, shortage of foreign currency for importation of materials and equipment, slow payment procedures adopted by the client in making progress payments, insufficient equipment, delay in relocating utilities, shortage of construction materials, delay in paying compensation to land owners, shortage of technical personnel, and delay in site mobilisation. The causes of delay are significant and should be given attention by client organisations, consultants and contractors to enable the timely completion of projects in future. It should also be noted that most of the causes of delay are not unique to Malawi, and have been observed in other southern African countries such as South Africa, Botswana and Swaziland. Recommendations are made to prevent similar causes of delay in future.
机译:进行了一项研究,以查明马拉维完成道路建设项目的延迟原因。进行了文献综述,得出了72种典型的延误原因,并向马拉维的客户,承包商和顾问代表发送了调查表。使用相对重要性指数(RII)和Spearman等级相关系数对结果进行了分析,结果表明马拉维延误的十大原因是:燃料短缺,承包商现金流量不足,用于材料进口的外币短缺以及设备,客户在进行进度付款时采用的付款程序缓慢,设备不足,公用事业搬迁延迟,建筑材料短缺,拖延向土地所有者支付赔偿金,技术人员短缺以及工地动员延迟。延迟的原因很重要,客户组织,顾问和承包商应引起重视,以确保将来能够及时完成项目。还应指出,大多数造成延误的原因并非马拉维独有,在其他南部非洲国家(如南非,博茨瓦纳和斯威士兰)也已观察到。提出建议以防止将来出现类似的延迟原因。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号