Mechanical Mechanism Analysis and Influencing Factors of Subway Cross Passage Construction

机译:地铁跨通道施工的力学机理分析及影响因素

获取原文
           

摘要

The construction of the cross passage changes the main tunnels segment from a complete cylindrical structure to a notched unstable stressed structure. Thus, the overall force (bending and shearing) performance of the main tunnels is considerably decreased. The excavation of the cross passage also destroys the stability of the original soil layer and main tunnels and causes difficulty in avoiding the settlement of the surface and main tunnels. Numerical simulation analysis of the mechanical characteristics and influencing factors analysis were carried out using FLAC3D. Results show that (1) the construction of the cross passage largely disturbs the main tunnels. The settlement of the intersection part of the main tunnels and cross passage is mainly concentrated from ?7 m to 7 m. (2) During the construction of the cross passage, the original main tunnels are subjected to stress redistribution, which causes stress concentration in the intersecting segments, especially in the opening side segment has an unfavorable force form in which the upper and lower sections are integrally pulled. (3) The construction of the cross passage causes a large tensile stress area in the structure as well. As a result, the overall tension of the upper and lower sections of the structure and the compression of the hance are unfavorable. (4) The influence of the excavation of the cross passage on the surface and main tunnels is related to the buried depth, intersection angle, excavation method, and grouting range. Therefore, the influence of different parameters can be analyzed by changing the model parameters.
机译:交叉通道的构造将主隧道段从完整的圆柱结构变为带缺口的不稳定受力结构。因此,主隧道的总力(弯曲和剪切)性能大大降低。交叉通道的开挖还破坏了原始土壤层和主要隧道的稳定性,并导致难以避免地面和主要隧道的沉降。使用FLAC3D进行了力学性能的数值模拟分析和影响因素分析。结果表明:(1)交叉通道的施工在很大程度上扰乱了主要隧道。主隧道与交叉通道的交叉部分的沉降主要集中在?7 m至7 m。 (2)在交叉通道的施工过程中,原来的主隧道承受了应力的重新分配,这导致相交段中的应力集中,特别是在开口侧段中,上部和下部一体形成的不利力形式拉。 (3)交叉通道的结构也会在结构中引起较大的拉应力区域。结果,该结构的上部和下部的总张力以及该框的压缩是不利的。 (4)交叉通道开挖对地表和主洞的影响与埋深,相交角,开挖方法和注浆范围有关。因此,可以通过更改模型参数来分析不同参数的影响。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号