Purpose - Traditionally, construction projects are awarded based on the lowest submitted tendering prices. However, this awarding method often causes problems on project delay, poor risk assessment and increased claims from variations. This paper aims to address these issues. Design/methodology/approach - Nowadays, clients require tenderers to submit both bidding prices and contract duration. This bidding method is called an optimal price-time bidding model, the details of which are investigated in this paper, using 24 Hong Kong private and public foundation price-time contracts.rnFindings - The results show that private foundation projects produce better time and cost savings when compared with public foundation projects, meaning that the former are generally more effective in using the optimal price-time bidding model than in public foundation projects. To further explore the effectiveness of the price-time bidding model, case studies from a private and a public foundation project are investigated to show that private foundation projects using the price-time bidding model are more effective than public foundation projects.rnOriginality/value - This paper encourages contractors to consider both time and cost factors in tendering and construction processes, noting that high liquidated and ascertained damages (LAD) charges need to be applied. This can provide a "balanced environment" for contractors in the construction industry.
机译:目的-传统上,建设项目是根据提交的最低投标价格授予的。但是,这种授予方法通常会导致项目延误,风险评估不佳以及变更索赔增加的问题。本文旨在解决这些问题。设计/方法/方法-如今,客户要求投标人同时提交投标价格和合同期限。这种投标方法称为最优价格-时间投标模型,本文使用24个香港私人和公共基金会的价格-时间合同对其细节进行了研究。研究结果-结果表明,私人基金会项目产生了更好的时间和成本。与公共基金会项目相比节省了资金,这意味着与使用公共基金会项目相比,前者在使用最佳价格时标模型方面通常更有效。为了进一步探讨价格竞标模型的有效性,对来自私人和公共基金会项目的案例研究进行了调查,结果表明,使用价格竞标模型的私人基金会项目比公共基金会项目更为有效。本文鼓励承包商在招标和施工过程中同时考虑时间和成本因素,并指出需要支付高额的违约金和确定的损害赔偿费。这可以为建筑业的承包商提供“平衡的环境”。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号