CPB CONTRACTORS PTY LTD v JKC AUSTRALIA LNG PTY LTD (NO 3)

机译:CPB承包商私人有限公司v JKC澳大利亚液化天然气私人有限公司(NO 3)

获取原文
获取原文并翻译 | 示例
           

摘要

For these reasons, CPB's application was dismissed, with costs. The appellant subcontractor was party to a contract with the respondent head contractor for engineering procurement, construction and commissioning works. The head contractor demanded payment of liquidated damages from the subcontractor arising from late completion of the works. The subcontractor disputed the head contractor's entitlement to the liquidated damages on the basis of the head contractor's assessment of the subcontractor's extension of time claims.
机译:由于这些原因,CPB的申请被驳回,并产生了费用。上诉分包商与被申请人总承包商签订了工程采购,建筑和调试工程合同。总承包商要求承包商分包因工程完工而产生的违约金。分包商根据总承包商对分包商的延期索赔的评估,对总承包商的违约金主张提出异议。