Understanding the role of 'tasks anticipated' in lookahead planning through simulation

机译:通过仿真了解“预期任务”在提前计划中的作用

获取原文
获取原文并翻译 | 示例
           

摘要

Construction planning takes place at many levels. This paper pertains to the level called lookahead planning, during which planners make their plan more realistic as construction tasks approach execution. To improve the quality of lookahead planning, the construction industry has benefited from implementing the Last Planner® System (LPS) that emphasizes creating reliable workflow. Successful lookahead planning relies on task anticipation by breaking down tasks to the level of operations, designing those operations, and making tasks ready by identifying and removing their constraints so that tasks can become executable assignments. This paper presents a study, using computer simulation, of the relationship between improving Task Anticipated (TA) in lookahead planning and overall project duration. The results indicate that increasing TA can have a positive influence on reducing project duration. The authors recommend that industry practitioners use the TA metric to gauge their planning performance and then to improve on it.
机译:施工计划在许多层面上进行。本文涉及称为超前计划的级别,在此级别中,随着施工任务的临近执行,计划人员使他们的计划更切合实际。为了提高前瞻性计划的质量,建筑行业从实施强调强调创建可靠工作流程的LastPlanner®系统(LPS)中受益。成功的超前计划依赖于将任务分解为操作级别,设计这些操作并通过识别和消除其约束使任务准备就绪,从而使任务成为可执行任务的任务预期。本文使用计算机仿真技术,对改善提前计划中的预期任务(TA)和总体项目工期之间的关系进行了研究。结果表明,增加技术援助可以对减少项目工期产生积极影响。作者建议行业从业人员使用TA指标来衡量其计划绩效,然后对其进行改进。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号