Evaluating the Project Completion Time When Non-Identical Beta Distributions Govern the Activity Networks

机译:评估项目完成时间,当非相同的测试版分布管理活动网络时

获取原文
获取原文并翻译 | 示例
           

摘要

The main purpose of this paper is to determine the project completion time using a recursive method, where the activity times are distributed according to a sequence of beta distributions with unequal location parameters. For this purpose, we first evaluate the kth moment of the maximum of independent random variables that follow this sequence of distributions. Some illustrative examples are presented to demonstrate the applicability and appropriateness of this generalized beta model. These examples show that, the suggested estimate of project completion time is situated between the lower bound estimate (PERT) and the upper estimate that was obtained by Kambarowski. Moreover, this estimate has lowest variance among the other known estimates. Comparisons with other exemplary estimates (e.g., exponential, Erlang and Weibull estimates), discussed in literature, are presented.
机译:本文的主要目的是使用递归方法确定项目完成时间,其中活动时间根据具有不等位置参数的β分布序列分布。为此目的,我们首先评估遵循此分布序列的独立随机变量的最大值的第kth矩。提出了一些说明性实施例以证明该广义β模型的适用性和适当性。这些示例表明,项目完成时间的建议估计位于下限估计(Pert)和Kambarowski获得的上估计之间。此外,该估计在其他已知估计之间具有最低的方差。展示了与文献中讨论的其他示例性估计(例如,指数,Erlang和Weibull估计数)的比较。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号