Statistical Time Estimates for Deepwater Completions in the Gulf of Mexico: Integration of Neural Networking and Distribution Modeling.

机译:墨西哥湾深水完井的统计时间估计:神经网络和分布模型的集成。

获取原文
获取原文并翻译 | 示例

摘要

Predicting completion time in deepwater wells is an imminent necessity in the modern well construction cycle. The primary objective of this thesis is to present a novel integrated approach of statistical analysis and neural networking to identify well characteristics for their impact on total time to complete a well.;Using a neural network, fifteen crucial attributes from the Dodson Database were used in this study and analyzed for relative impact with respect to time. These attributes included primary parameters such as well depth and interval number. Wells in the database were assigned a value, depending on their fifteen attributes, that correlated to length of time to complete.;The program designated prospect wells a value using the same time weighted impact system, as well as the same impact parameters. Wells within the database with most similar values to the prospects were used in the statistical analysis for total completion time. Actual data were used for the 15 parameters in the program for "Dark Star," "Liberty," and "Terrapin" to test the reliability of the statistical analysis. Estimates for "Dark Star" and "Liberty," which were completed in 2014, were within 5% of field completion time. "Terrapin" is yet to be completed; however, the programs estimate was within 3% of the Approval For Expenditure (AFE). With access to the data provided by Stone Energy as one of the active operators in GOM, this thesis presents a valuable methodology to estimate completion time.
机译:预测深水井的完井时间是现代井建设周期中的迫切需要。本文的主要目的是提出一种新颖的统计分析和神经网络集成方法,以识别井特征对完井总时间的影响。;使用神经网络,从Dodson数据库中使用了15个关键属性。这项研究并分析了时间方面的相对影响。这些属性包括主要参数,例如井深和层数。数据库中的油井根据其十五个属性被分配了一个值,该值与完成时间相关。该程序使用相同的时间加权冲击系统和相同的冲击参数指定探井一个值。在数据库中与预测值最相似的井用于总完成时间的统计分析。程序中的“暗星”,“自由”和“ Terrapin”的15个参数使用了实际数据,以测试统计分析的可靠性。 2014年完成的“暗星”和“自由”的估算距离现场完成时间不到5%。 “ Terrapin”尚未完成;但是,该计划的预算在支出批准(AFE)的3%之内。通过访问Stone Energy作为GOM中活跃的运营商之一提供的数据,本文提出了一种有价值的方法来估算完成时间。

著录项

  • 作者

    Robinson, Paul Kelly.;

  • 作者单位

    University of Louisiana at Lafayette.;

  • 授予单位 University of Louisiana at Lafayette.;
  • 学科 Petroleum engineering.;Statistics.;Ocean engineering.
  • 学位 M.S.
  • 年度 2014
  • 页码 340 p.
  • 总页数 340
  • 原文格式 PDF
  • 正文语种 eng