针对省内泵站设计工程投资及单位kW投资差别较大的情况,通过对2座泵站进行设计总结,浅谈影响泵站工程投资的主要因素。结果表明:枢纽布置、征地移民补偿费与接入系统专项等是影响泵站工程投资的主要因素。在设计中应通盘考虑,尽量使泵站总体方案技术可行、经济合理。%In view of the huge disparity in investment for per kW and total investment among pumping station projects in Guangdong Province , by summarizing the design of two pumping stations , the mai factors on project investment of pumping station are discussed in this paper .In order to achieve a technically feasible and economically viable overall design scheme of pumping station , the project layout , compensation fee for land acquisition & resettlement and interconnection system are the main influencing factors which should be thoroughly considered in the project design .