浅埋超近距离交叉隧道施工顺序数值模拟研究

         

摘要

以长沙西北下行联络线罗家一号隧道下穿新建杭长正线曾家岭一号隧道为工程背景,运用数值分析手段对浅埋条件下超近距离立体交叉隧道的施工顺序进行了详细分析。通过不同计算工况下围岩和衬砌结构位移场、应力场以及围岩塑性区的对比分析,得到“先下后上(先施工下洞后施工上洞)”的施工顺序明显优于“先上后下(先施工上洞后施工下洞)”的施工顺序。最后将该研究成果应用于工程实践指导施工,目前该工程已经顺利竣工,说明该文提出的施工顺序是可行的,安全可靠的。%Based on the project of Luojia tunnel 1 to Zengjialing tunnel 1 in Northwestern Changsha, construction order for shallow buried interchange tunnels with extra close distance is analyzed in detail. Through the comparison and analysis on the surrounding rock, displacement field of lining struc-ture, stress field and plastic zone of surrounding rock, it is known that construction order of"down first, up second"is superior than that of"up first, down second". The study result is applied to guide the construction and achieve the final goal. It is proved that the construction order presented is feasible and reliable.

著录项

相似文献

  • 中文文献
  • 外文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号