The Last Planner(TM) System (LPS) has been implemented on construction projects to increase work flow reliability, a precondition for project performance against productivity and progress targets. The LPS encompasses four tiers of planning processes: master scheduling, phase scheduling, lookahead planning, and commitment / weekly work planning. This research highlights deficiencies in the current implementation of LPS including poor lookahead planning which results in poor linkage between weekly work plans and the master schedule. This poor linkage undermines the ability of the weekly work planning process to select for execution tasks that are critical to project success. As a result, percent plan complete (PPC) becomes a weak indicator of project progress.The purpose of this research is to improve lookahead planning (the bridge between weekly work planning and master scheduling), improve PPC, and improve the selection of tasks that are critical to project success by increasing the link between Should, Can, Will, and Did (components of the LPS), thereby rendering PPC a better indicator of project progress.The research employs the case study research method to describe deficiencies in the current implementation of the LPS and suggest guidelines for a better application of LPS in general and lookahead planning in particular. It then introduces an analytical simulation model to analyze the lookahead planning process. This is done by examining the impact on PPC of increasing two lookahead planning performance metrics: tasks anticipated (TA) and tasks made ready (TMR). Finally, the research investigates the importance of the lookahead planning functions: identification and removal of constraints, task breakdown, and operations design.The research findings confirm the positive impact of improving lookahead planning (i.e., TA and TMR) on PPC. It also recognizes the need to perform lookahead planning differently for three types of work involving different levels of uncertainty: stable work, medium uncertainty work, and highly emergent work.The research confirms the LPS rules for practice and specifically the need to plan in greater detail as time gets closer to performing the work. It highlights the role of LPS as a production system that incorporates deliberate planning (predetermined and optimized) and situated planning (flexible and adaptive).Finally, the research presents recommendations for production planning improvements in three areas: process related- (suggesting guidelines for practice), technical- (highlighting issues with current software programs and advocating the inclusion of collaborative planning capability), and organizational improvements (suggesting transitional steps when applying the LPS).
机译:Last Planner(TM)系统(LPS)已在建筑项目上实施,以提高工作流程的可靠性,这是实现针对生产力和进度目标的项目绩效的前提。 LPS包含四层计划流程:主计划,阶段计划,提前计划和承诺/每周工作计划。这项研究突出了当前LPS实施中的缺陷,包括不良的超前计划,这导致每周工作计划与主计划之间的关联性很差。这种不良的联系削弱了每周工作计划流程选择对项目成功至关重要的执行任务的能力。因此,完成计划百分比(PPC)成为项目进度的较弱指标。本研究的目的是改善超前计划(每周工作计划与主计划之间的桥梁),改善PPC并改进任务选择通过增加Should,Can,Will和Did(LPS的组成部分)之间的联系,对项目成功至关重要,从而使PPC可以更好地指示项目进度。该研究采用案例研究方法来描述当前实施中的缺陷LPS的建议,并提出有关在总体上,尤其是在提前规划中更好地应用LPS的指南。然后,它引入了一个分析模拟模型来分析超前计划过程。这是通过检查增加两个提前计划性能指标对PPC的影响来完成的:预期任务(TA)和已完成任务(TMR)。最后,本研究调查了超前计划功能的重要性:确定和消除约束,任务分解以及运营设计,这些研究结果证实了改善超前计划(即TA和TMR)对PPC的积极影响。它还认识到需要对三种类型的涉及不同程度不确定性的工作进行不同的前瞻性计划:稳定工作,中等不确定性工作和高度紧急工作。研究确认了LPS的实践规则,尤其是需要更详细地计划随着时间越来越接近完成工作。它强调了LPS作为包含有计划的计划(预定和优化)和位置的计划(灵活的和适应性的)的生产系统的作用。最后,该研究提出了三个方面的生产计划改进建议:过程相关-(实践建议指南) ),技术-(当前软件程序的突出问题并主张纳入协作计划功能)和组织改进(建议在应用LPS时建议采用过渡步骤)。

著录项

  • 作者

    Hamzeh, Farook Ramiz.;

  • 作者单位

    University of California, Berkeley.;

  • 授予单位 University of California, Berkeley.;
  • 学科 Engineering Civil.
  • 学位 Ph.D.
  • 年度 2009
  • 页码 271 p.
  • 总页数 271
  • 原文格式 PDF
  • 正文语种 eng
  • 中图分类
  • 关键词

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号