Assessment of Ground Condition for a Mass Rapid Transit System in Singapore

机译:新加坡地铁系统地面条件评估

获取原文
获取原文并翻译 | 示例

摘要

Subsurface ground conditions will have a large influence on the design of underground structures suchrnas tunnelling and deep excavation works. Adequate site investigation information is very useful inrnunderstanding the ground conditions. For the on-going mass rail transit system Circle Line Stage 2 -rnContract 823 project, close to 90 exploratory boreholes were sunk to investigate the ground condition.rnThe project involves the construction of 3 underground MRT stations and twin bored tunnels ofrnapproximately 2.5 km long. The objectives of the site investigation were to obtain a betterrnappreciation of the ground subsurface profile along the route of the project and to ascertain designrnparameters. The results obtained from the site investigation are summarised in this paper.rnThe marine clay layer is the predominant soft soil layer found at the site. The maximum thicknessrnencountered in the site investigation is about 30 metres. One of the most interesting findings from thernsite investigation were evidence of possible occurrence of some previous earthslips of Old Alluviumrnhillocks that had taken place during the initial stage of the Holocene period, i.e. before the depositionrnof the Lower Marine Clay layer, and are now buried between Kallang Formation soils. Thesernearthslips had caused huge volume of soils displaced into adjacent valleys. Some of these "buriedrnvalleys" are now filled with intact Old Alluvium soils, which have undergone moderate degree ofrnweathering albeit the soil fabric of the parent material remains relatively undisturbed. Thisrnextraordinary finding is described in the paper.rnThe paper also presents evaluation of the characteristics and properties for some of the main soil typesrnthat are encountered in the project.
机译:地下地面条件将对地下隧道的设计和深挖工程产生很大影响。充分了解现场情况对现场调查非常有用。对于正在进行中的轨道交通系统“环线2期-合同823”项目,沉没了近90个探索性钻孔,以研究地面状况。该项目涉及3个地下地铁站和长约2.5公里长的双孔隧道的建设。现场调查的目的是沿工程路线更好地了解地下地下轮廓,并确定设计参数。本文总结了现场调查的结果。rn海洋黏土层是现场发现的主要软土层。现场调查中发现的最大厚度约为30米。现场调查中最有趣的发现之一是证据表明,在全新世初期,即下海洋粘土层沉积之前,已经发生了一些旧冲积土的先前滑坡,这些滑坡现在被埋在加冷之间地层土壤。这些泥石流导致大量土壤流失到相邻的山谷中。现在这些“埋谷”中的一些已被完整的旧冲积土填充,尽管母体的土壤结构相对不受干扰,但这些土壤已经历了中等程度的风化作用。本文还描述了这种非凡的发现。本文还介绍了对项目中遇到的一些主要土壤类型的特征和特性的评估。

著录项

相似文献

  • 外文文献
  • 中文文献
  • 专利
获取原文

客服邮箱:kefu@zhangqiaokeyan.com

京公网安备:11010802029741号 ICP备案号:京ICP备15016152号-6 六维联合信息科技 (北京) 有限公司©版权所有
  • 客服微信

  • 服务号